7-day Project Calendar Not Cooperating 

Additional Details

7-day Project Calendar Not Cooperating

I'm a bit stumped. I have a 7-day calendar for curing concrete but P6 is taking my duration and dividing by 3. In other words, it thinks I am working three 8-hour shifts every day. I went into the project calendar and changed the workday to 8 hours for every month of the project, but the problem continues. What else could be causing this problem? Thanks in advance.
 

Asked in Primavera - 510 days ago

Tags: Primavera Project Calender 