Civil Engineering Technical Questions Answers - Ask a Civil Engineer

summing cost accounts in P6 

Additional Details

summing cost accounts in P6.
I have assigned cost accounts to resources, eg: concrete resource to concrete account, steel resource to steel account, etc.
now, after entering actuals for resources, can I put these actuals in the corresponding cost account, & then sum all the actuals for the same cost account?
eg: we have activity a,b,c, & the three of them have concrete resource associated with concrete cost account.
now, activity a has 30$ actuals of concrete resource, activity b has 50 $ actuals, now can I put the actuals form a & b ( 30+50 = 80) in the cost account?
 

Asked in Primavera - 331 days ago

Tags: Primavera 

Answer now
Report abuse
Rate this : 0 0

Ask a Question